|
Courthouse deadline extended
By Douglas Sweeney
Lexington and Rockbridge County were granted a six-month extension of
all courthouse-related deadlines by Circuit Court Judge Everett Martin
at a hearing on Tuesday.
The localities hope that the extra six months will allow them to modify
the exterior of the courthouse. The appearance of the proposed
courthouse at the corner of Randolph and Nelson streets has met with
heavy disapproval from local residents, some of whom have described the
design as “inappropriate” and “ugly.”
If the city and county can not come up with a “Plan B,” as Martin
described it, in six months then they will be forced to build “Plan A,”
meaning the current design for the Randolph-Nelson site.
Martin said that if another alternative is not reached in six months
then “this is your courthouse,” referring to a schematic drawing of the
current design that he held aloft.
With the extension, construction must begin by Dec. 20 and the facility must
be completed by Oct. 22, 2008.
The localities filed the motion for the extension in February to address
the public outcry over the cost, architectural style, and size of the
proposed courthouse design.
Ford Stephens, attorney for the Commonwealth of Virginia, opposed the
extension. He began his argument with a brief history of the
courthouse’s need for repair. According to Stephens, the need for a new
facility was first identified in 1974 when Judge Holstein wrote a
letter to the county Board of Supervisors in which he commented on the
“disrepair” of the courthouse.
Stephens' main reasons for opposing the extension were that the
current court facilities were “deficient” and extending the use of them
is unsafe. Also, Stephens expressed his fear that this extension will
beget another and another.
He also addressed concerns about cost, style, and size. Stephens said
that cost was “not a relevant factor” for granting an extension. He
noted that Virginia requires its courts to be “safe and sufficient,” not
inexpensive.
As for architectural style, Stephens argued that it was not a reason to
prolong the use of an unfit courthouse any longer than necessary.
Stephens said the size was dictated by the two localities based on a
report from the panel they created.
Stephens emphasized the need for a resolution to the courthouse
situation when he said, “I’m just trying to bring an end to a process
which began when I was 12."
Lexington city attorney Larry Mann and Rockbridge County attorney Vickie
Huffman argued on behalf of the two localities. Mann emphasized that the
six months were merely for modifications to the existing design, not for
starting the design process over.
Mann also mentioned the unexpected difficulties that led to the need for
an extension. Specifically, he mentioned the added burden put on the
architects of keeping the parking deck and courthouse separate, because
the city owns the former and the county the latter.
When asked by Martin if the city and county had a specific plan
formulated at this point, Mann responded, “No sir, that is what we need
the six months for.”
After hearing both sides of the debate, Martin ruled in favor of the
localities, granting them the desired extension. With the extension came
a provision that the localities submit monthly progress reports to the
commonwealth.
After the six months if there is a “Plan B” that receives Virginia’s
approval, then “Plan B” will be the new courthouse. If, however, the
commonwealth does not approve the new plan, then Martin would choose
between “Plan A” and “Plan B” at trial. And if no “Plan B” materializes,
the localities will be forced to build the highly unpopular “Plan A,”
the current design for the Randolph-Nelson site. |

Feb. 9, 2006
Delay sought on
courthouse construction
Jan. 26, 2006
Debate rages over courthouse plans

Mar. 26, 2005
New plans for rebuilding county
courthouse 
Oct. 11, 2003
Courthouse compromise
Nov. 14, 2002
Judge begins courthouse renovation
process
Sept. 19, 2002
Voters to judge courthouse plan |